← BuildingShanny Advisory · The library

Design and consultant fees on a build in Bali

Shanny Poijes · Developer in Indonesia (director, PT Core Group Indonesia) · Background in project management and advisory
Last verified 15 August 2026 · checked for changes 21 November 2026

The regulations cited on this page fix who must do the design work and how the fee is taxed. None of them sets the fee itself.

A certified planning provider must prepare the technical plan for the PBG (the building approval). A supervision consultant must follow the build and sign the fitness statement at the end. Those are two separate roles.

The published reference for architects is the fee guide of the Indonesian architects' association. It is a percentage scale that falls as the project gets larger. It is a guide and not law.

What the law says

PP 16/2021, Article 252(1)

Government Regulation 16 of 2021 implements the Building Law. Technical planning for a PBG is done by a certified planning provider.

PP 16/2021, Article 187

The technical plan covers architecture, structure, utilities and specifications. The structural calculation includes a soil investigation for buildings over 2 storeys.

PP 16/2021, Articles 59 and 60(6)

A supervision or construction management consultant approves preparation documents, notifies the regency at each stage and issues the statement of fitness for use.

PP 9/2022, Article 3

Construction consultancy covers design, quantity surveying and project management. Final income tax on it is 3.5% for a provider with a business certificate or a certified individual. It is 6% for a provider without one.

UU PPh (Income Tax Law), Article 26

Fees paid to a foreign consultant carry withholding tax of 20%, or the rate in an applicable tax treaty.

What it means

Expect at least four design scopes on a permitted build: architecture, structure, utilities and specifications. Ask each bidder which of the four its fee covers.

Supervision is a separate role from design. The supervisor's signature is what the SLF (the certificate of fitness) rests on.

A consultant's certification changes the tax on its fee. The rate is 3.5% with a certificate and 6% without, so ask which applies before comparing quotes.

A designer based abroad is taxed differently. Withholding at 20% or a treaty rate applies to the fee. Ask a tax adviser who withholds it and how.

The drawing package for the PBG is a consultant cost. It is separate from the PBG fee the regency charges.

A soil investigation is its own line for buildings over 2 storeys. Check that someone has priced it.

In practice

Practitioners report. This is what the market and the desks do, which is not the same as the written law.

The Indonesian architects' association (IAI) fee table, 2007 edition, is still the published scale, as shown on iai-jatim.com. Its category 3 covers private houses and hotels. There the fee is 8.00% for projects up to Rp 200 million, 6.48% at Rp 2 billion and 5.60% at Rp 4 billion.

The same table continues to 4.92% at Rp 20 billion and 3.18% at Rp 100 billion for category 3. For category 2, apartments and offices, it shows 7.00% up to Rp 200 million and 4.52% at Rp 20 billion. Social buildings are at most 2.5%.

The table is the association's own guide. It is not a legal tariff.

What to check

  • Ask each consultant for its certification and which tax rate applies to its fee.
  • Ask each bidder to list the drawings, calculations and specifications its fee includes.
  • Confirm who prepares the PBG upload and whether that is inside the design fee.
  • Appoint the supervision consultant in writing before work starts.
  • Check whether a soil investigation is priced, and by whom.
  • Ask a tax adviser about withholding before paying any designer outside Indonesia.
  • Compare any percentage fee with the architects' association table for the same building category.

Downloads

Design checklist (PDF)

Questions

What percentage do architects charge in Indonesia?

The regulations cited on this page set no rate. The architects' association table, 2007 edition, covers private houses and hotels. It shows 8.00% up to Rp 200 million, falling to 3.18% at Rp 100 billion.

Is the architects' fee table binding?

It is the association's own published guide and not a regulation. Check what your appointment says about the fee.

What tax applies to a design fee?

PP 9/2022 Article 3 sets final income tax on construction consultancy at 3.5% with a business certificate and 6% without. A foreign consultant's fee carries 20% withholding or a treaty rate.

Do I need a separate supervision consultant?

PP 16/2021 gives the supervision or construction management consultant its own duties, including the fitness statement for the SLF. It is a separate role from the planner.

Sources

General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.

Read nextThe library

Who signs the drawings and engineering for a PBG and an SLF

A certified planner prepares the technical plan for the PBG. The supervising consultant issues the fitness statement for the SLF.

Taxes and statutory charges on building a villa in Bali

A VAT-registered contractor charges 11% PPN. A self-build of 200 m2 or more pays 2.2% on build costs. PPh final, BPJS and the PBG fee also apply.

PBG: the building approval in Bali and whose name it is in

A PBG is issued to the building owner before construction. It cannot be moved to another name. Anyone can request a copy from the regency.

What a construction contract must contain under Indonesian law

UU 2/2017 Article 47 lists 16 items every construction contract must cover. The contract is in Indonesian, plus English with a foreign party.