The relationship between the party ordering the work and the contractor must be set out in a construction contract. The Construction Services Law lists 16 items the contract must cover at a minimum.

The contract is made in Indonesian. With a foreign party it must be in Indonesian and English, and in a dispute the Indonesian text is used.

The contract is subject to Indonesian law. A privately financed project may use standard documents as the parties agree.

What the law says

UU 2/2017, Article 46(1)

Pengaturan hubungan kerja antara Pengguna Jasa dan Penyedia Jasa harus dituangkan dalam Kontrak Kerja Konstruksi.

This is Law 2 of 2017 on Construction Services. The working relationship between service user and service provider must be set out in a construction contract.

UU 2/2017, Article 47(1)

The 16 minimum items start with the parties, the work, the period of performance and maintenance, equal rights and duties, certified workers, payment and default. They continue with settling disagreements, termination, force majeure, building failure, worker protection and third-party protection. The last three are the environment, guarantees for risk and legal liability, and the choice of dispute forum.

UU 2/2017, Article 48

A contract for planning services must also deal with intellectual property. A contract with a foreign party holds a duty of technology transfer.

UU 2/2017, Article 50(1) to (3)

Dalam hal terjadi perselisihan dengan pihak asing sebagaimana dimaksud pada ayat (2) digunakan Kontrak Kerja Konstruksi dalam bahasa Indonesia.

The contract is made in Indonesian. With a foreign party it must be made in Indonesian and English. In a dispute with the foreign party, the Indonesian contract is used.

UU 2/2017, Article 65(4), with PP 22/2020, Article 87

The period of liability for building failure must be stated in the contract. The planned life of the structure must be stated clearly in the design documents and set out in the contract.

PP 22/2020, Article 75(2)

The implementing regulation states that a construction contract is subject to the law in force in Indonesia.

PP 22/2020, Article 76

The contract is a set of documents, holding at least the signed agreement, special conditions and general conditions. It also holds the user's specification, drawings and bill of quantities, and the provider's offer. Clarification minutes, the letter of acceptance and the provider's statement of ability complete the set.

PP 22/2020, Article 77, as replaced by PP 14/2021

Contracts financed by state money use standard documents. Contracts financed by non-state money may use standard documents as the parties agree.

What it means

Use Article 47 as a checklist. A one-page quotation signed by both sides will not cover 16 items.

The agreement must list the binding documents and their order of precedence. Decide which wins when the drawings, the specification and the bill of quantities disagree.

State the payment system. The regulation recognises advance, progress, milestone and turn-key payment, and the terms must hold the payment period and compensation for late payment.

State how the work is valued. A lump sum is a fixed price for agreed work, and it changes only with an agreed change of scope. A unit price contract is paid on joint measurement of work actually done.

Write the planned life of the structure and the building-failure period into the contract. The provider's statutory liability runs for at most 10 years from final handover where the planned life exceeds 10 years.

Sign Indonesian and English together when a foreign party is involved. The general language rule lets the parties agree which language governs, under Presidential Regulation 63/2019 Article 26(4). The construction law is narrower and points to the Indonesian text in a dispute.

How a court treats an English-prevails clause in a construction contract is a question for a lawyer. Do not assume the general rule wins.

The same Article 47 list applies to a contract between a contractor and its subcontractor.

In practice

Practitioners report. This is what the market and the desks do, which is not the same as the written law.

Practitioners report a cautious choice for any contract with an Indonesian party. The Indonesian and English texts are signed at the same time, with the Indonesian text prevailing.

Commentary on Supreme Court Circular 3/2023 reports its position on a missing Indonesian translation. Alone, it is not a ground to annul an agreement unless bad faith is proven. The duty to prepare an Indonesian version remains.

What to check

  • Compare the draft against the 16 items in Article 47(1) one by one.
  • Check that the contractor's legal name and identity match its company documents.
  • List the contract documents and state their order of precedence.
  • State the payment system, the payment period and the remedy for late payment.
  • State the planned life of the structure and the building-failure liability period.
  • Prepare the Indonesian and English texts together and sign both at once.
  • Stamp each signed original and state who pays the stamp duty.
  • Have an Indonesian construction lawyer review the dispute and language clauses before signing.

Downloads

Contractor setup checklist (PDF)

Questions

Must a construction contract in Indonesia be in Indonesian?

Yes. UU 2/2017 Article 50 requires Indonesian, and Indonesian plus English where a foreign party is involved.

Which language prevails in a construction dispute?

Article 50(3) says the Indonesian contract is used in a dispute with the foreign party. Ask a lawyer before relying on an English-prevails clause.

Can I use a FIDIC or other standard form for a private villa?

A privately financed contract may use standard documents as the parties agree. Whatever the form, it must cover the Article 47 items, be in Indonesian, and is subject to Indonesian law.

Does the law fix lump sum or unit price?

No. PP 22/2020 Article 82 lists lump sum, unit price, a combination, percentage of value, cost reimbursable and target cost. The parties choose.

Do the rules apply to subcontracts?

Yes. Article 49 applies the Article 47 list to contracts between a provider and its sub-provider.

Sources

General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.

Read nextThe library

How long is a contractor liable for building failure in Indonesia?

A contractor answers for building failure for the planned life of the structure, capped at 10 years from final handover under UU 2/2017.

Which language must a contract in Indonesia be written in?

A contract with an Indonesian party must be in Indonesian. A foreign party adds its own language or English, and the parties agree which text prevails.

Insurance during and after a build in Indonesia

The contract must cover worker social security and risk guarantees. Project cover with BPJS Ketenagakerjaan is charged on contract value.

Arbitration clauses and enforcing a foreign award in Indonesia

Commercial disputes can be arbitrated in Indonesia. A foreign award needs an exequatur from the Central Jakarta District Court before it can be enforced.