Taxes and statutory charges on building a villa in Bali
Which taxes apply depends on who builds. A contractor that is a registered VAT business (PKP) adds PPN, the value added tax, at an effective 11% to its invoice.
Self-build VAT (PPN KMS) covers a building of 200 m2 or more built outside the course of business. It applies where no PKP contractor collects PPN on the work. The rate is 2.2% of the build costs, and the only cost left out of the base is land acquisition.
Three more lines apply in both cases. The contractor bears final income tax on its revenue, the project carries social security cover for workers, and the regency charges a PBG fee.
What the law says
PMK 131/2024, Article 3
The statutory PPN rate is 12% from 1 January 2025. For non-luxury goods and services the tax base is 11/12 of the price, which gives an effective 11%. This Minister of Finance regulation applies to a PKP contractor's invoice.
Final income tax on construction work is 1.75% for a provider with a small-qualification business certificate or a certified individual. It is 4% for a provider with no certificate and 2.65% for all others. Construction consultancy is 3.5% with a certificate and 6% without.
PMK 81/2024, Article 323(3) and (4)
Self-build means building or extending a building outside the course of business or work, for use by the builder or by others. It applies to a fixed structure of timber, concrete, brick or steel, for dwelling or business, of 200 m2 or more.
PMK 81/2024, Article 323(5) and (6)
A building may be built at once or in stages. Stages more than 2 years apart count as separate buildings.
PMK 81/2024, Article 323(7) to (9)
Self-build includes building done by another party that does not collect PPN. A party that must collect PPN does so. The owner can be excused from the self-build tax by giving correct data on that party, at least its identity and full address.
PMK 81/2024, Article 324(3)
The base is all costs incurred or paid to build, in each tax month until completion. The only exclusion is the cost of acquiring the land.
PMK 11/2025, Article 20, as amended by PMK 53/2025
The self-build rate is 2.2%, being 20% x 11/12 x 12%. Under the transition rules of PMK 81/2024, the rate in force on the deposit date applies.
PMK 81/2024, Articles 325, 326, 328 and 331
The tax runs from the start of building to completion, deposited by the 15th of the following month under the builder's own tax number. A builder that is not a PKP is treated as having reported by paying. PPN paid on materials and services for the self-build cannot be credited.
What it means
State the tax basis next to every price you compare. A quote that includes PPN and a quote that excludes it are not the same number.
A common claim is that PPN on construction is 12% since 2025. The statutory rate is 12%, but the 11/12 base keeps the effective rate at 11% on non-luxury services. A 12% line on a villa contract over-charges.
A second common claim is that self-build VAT is 2.4%. That was the figure as PMK 81/2024 was first enacted, and the rate is now 2.2%. Builders, labour gangs or a company may do the work, as long as no PPN has been collected on it.
A business that passes Rp 4.8 billion of turnover in a book year must register as PKP. PMK 164/2023 Articles 17 and 18 start its PPN duty in the next book year. Keep the contractor's identity and full address on file.
Owner-supplied materials sit inside the self-build base. So do permit costs, according to the tax office's public help channel.
The social security agency charges construction projects on contract value. Work accident cover runs from 0.21% for contracts up to Rp 100 million down to 0.09% above Rp 5 billion. Death cover runs from 0.03% down to 0.01%.
The PBG fee is a regency charge. In Badung, Regional Regulation 7/2023 Articles 94 to 97 and Annex VIII set the formula. Regional Regulation 8/2025 amended Article 96 from 1 January 2026 and left Annex VIII unchanged.
The Badung formula multiplies floor area by a locality index of 0.5% of a standard unit price. Indices for function, complexity, permanence, height and ownership then apply. The regent sets the standard unit price each year.
In practice
Practitioners report that the deciding question is whether a PKP contractor builds. If so, the contractor charges 11% PPN. If not, the self-build tax applies.
Tax office outreach on self-build VAT for new villas has been reported from a Bali regency tax office. Expect the question to be asked.
What to check
- Ask each bidder in writing whether it is a PKP and whether its price includes PPN.
- Ask each bidder which final income tax rate applies to it and why.
- Confirm the floor area against the 200 m2 self-build threshold.
- Keep monthly cost records from the first day of building if self-build applies.
- Deposit self-build VAT by the 15th of the following month under the builder's own tax number.
- Ask the contractor for the project's social security certificate.
- Ask the regency for the current standard unit price used in the PBG fee.
- Take the structure to a tax adviser before signing, because the finance ministry regulations are amended often.
Downloads
What is the VAT rate on construction in Indonesia?
A PKP contractor charges an effective 11%. The statutory rate is 12% applied to a base of 11/12 of the price for non-luxury services.
What is PPN KMS?
It is VAT on self-build. It applies to a building of 200 m2 or more that no PPN-collecting contractor builds. The rate is 2.2% of build costs excluding land acquisition.
Is land included in the self-build tax base?
No. PMK 81/2024 Article 324(3) excludes the cost of acquiring the land. It excludes nothing else.
Who pays PPh final on a construction contract?
It is tax on the contractor's income, at 1.75%, 2.65% or 4% depending on the contractor's certification. Contractors price it into their fee.
Does self-build VAT apply on leased land?
Yes. PMK 81/2024 Article 323 defines the tax by the building activity. It sets no condition on the type of land right.
- Government Regulation (PP) 9 of 2022 on income tax on construction services
- Minister of Finance Regulation (PMK) 81 of 2024, Articles 323 to 331, official text on the BPK regulations database
- Minister of Finance Regulation (PMK) 131 of 2024 on the VAT base
- Minister of Finance Regulation (PMK) 11 of 2025, as amended by PMK 53 of 2025
- Minister of Finance Regulation (PMK) 164 of 2023, Articles 17 and 18, on the duty to register for VAT
- Minister of Finance Regulation (PMK) 197 of 2013 on the small-business limit for VAT
- BPJS Ketenagakerjaan, construction services programme page, bpjsketenagakerjaan.go.id/jasa-konstruksi.html
- Badung Regional Regulation (Perda) 7 of 2023 on regional taxes and charges, Articles 94 to 97 and Annex VIII, as amended by Perda 8 of 2025
General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.