A rice field can carry three separate locks, starting with the national protected rice-field map, called LSD. The second is LP2B, protected farmland designated in the spatial plan. The third is the zone in the RDTR, the detailed plan.

A release letter from the Ministry of Agrarian Affairs touches the first lock only. It is not a zoning change. It is not a KKPR (the spatial approval) and not a building approval.

Land already designated LP2B cannot use the release route at all. National law allows its conversion only for public interest or national strategic projects.

The rules are moving. Perpres 4/2026 replaced the presidential regulation on rice-field conversion in February 2026. A revision of the procedure went to public consultation from 29 September to 29 October 2026.

What the law says

Permen ATR/BPN 2/2024, Article 12

A recommendation for change of land use is open only to LSD land not yet designated LP2B.

Permen ATR/BPN 2/2024, Article 13

The application goes to the Minister through the Director General. The file includes proof of ownership and a statement of planned use. It also includes a signed commitment to build within three years.

Permen ATR/BPN 2/2024, Article 15(5) to (8)

There are three outcomes: convertible, convertible with conditions, or not convertible. The answer is not convertible where the plan shows a food-crop or protected zone on existing rice field.

Permen ATR/BPN 2/2024, Article 15(10) to (12) and Article 27

The recommendation is issued by ministerial decision within 14 days of a complete file. Monitoring can suspend or revoke it and order the rice field restored.

UU 41/2009, Article 44

This is the law on protection of sustainable food farmland. As amended, it allows LP2B conversion only for public interest or national strategic projects.

Perda Bali 4/2026, Article 13(2) to (4)

Productive land designated in the spatial plans may not be converted. The exceptions are strategic national policy, public-interest land procurement and disaster relocation. A land-short owner may build solely a dwelling.

Perda Bali 4/2026, Article 20

Sanctions are administrative. They include a halt, closure, permit revocation, demolition and restoration of land function. A fine is listed with no amount set. Article 20(5) adds that criminal sanctions under other laws may apply.

Perbup Gianyar 1/2024 (RDTR Tegallalang), LP2B special provision

Tidak diperbolehkan kegiatan alih fungsi lahan pertanian menjadi lahan terbangun

This is how one detailed plan writes the lock. Inside the LP2B area, converting farmland into built land is not allowed. The same plan marks a villa as not allowed in food-crop zone P-1.

What it means

A release letter is not a zoning change. The zone changes only when the regency revises its RDTR, with the Minister's approval of substance.

A plain yes needs a zone that already fits the plan, plus one more ground. Grounds include a valid KKPR for non-farm use, a non-farm title, or an existing building or fill.

Where the zone does not fit, the answer is at best conditional. The spatial plan must then be brought into line.

The Minister was quoted on 7 November 2025 on physical rice fields. If the land is still rice field, no permit follows. That holds even where the regency plan already shows another use.

The national development plan sets a floor. Regencies must designate at least 87% of their baseline rice fields as LP2B. A plot on the LSD map alone can become LP2B when the regency revises its plan.

Perda Bali 4/2026 has been in force since 24 February 2026, with no transitional provisions. The elucidation of Article 13(2) caps exceptions at 20% on non-ricefield farm zones.

The draft revision would add a regency letter that the plot is outside LP2B, plus polygon coordinates. It is a draft, not law.

In practice

Practitioners report. This is what the market and the desks do, which is not the same as the written law.

Practitioners report that a plot zoned residential can still sit on the LSD map. A regency validation can then treat it as only partly conforming until the ministry recommendation issues.

What to check

  • Check the plot against the LSD map and against the LP2B designation, as two separate questions.
  • Read the zone code in the RDTR and the activity table row for your use.
  • Ask who the applicant for the release is and for the application receipt number at the Ministry.
  • Ask which ground under Article 15 the application relies on.
  • Read the signed three-year build commitment and the use it names.
  • Check whether the regency is revising its spatial plan to meet the LP2B floor.
  • Confirm the current national regulation and procedure on the date you rely on a release.
Questions

Can I build a villa on a rice field in Bali?

Only if the land is outside LP2B, the zone allows a villa and the LSD lock is released. Where the plan shows a food-crop zone and the land is rice field, the release is refused.

Does an LSD release letter make the land buildable?

No. It removes one lock. The zone, the KKPR and the building approval are still tested against the spatial plan.

Does Perda Bali 4/2026 carry a penalty of five years and Rp 1 billion?

No. That claim circulates but is not in the text. The regulation's own sanctions are administrative, and it sets no fine amount.

Sources

General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.

Read nextThe library

How zoning works in Bali

Bali zoning is a stack of plans. The zone code sets the permitted use. Coastal, cliff, temple and farmland overlays decide what you can build.

How to check the zoning of a plot in Badung, Bali

Badung regency runs a public zoning service. For a parcel it returns the zone, farmland overlay, building ratios, setbacks, height and permitted uses.

The Bali construction moratorium: what it is and what it is not

Bali's moratorium on tourism accommodation covers six regencies and farmland island-wide. It runs on directives, with no published instrument.

Nominee arrangements in Bali: why they are void and banned

A nominee holds land for a foreign beneficial owner. National law voids the transfer, and Perda Bali 4/2026 bans facilitating it.