← Land use and zoningShanny Advisory · The library

How zoning works in Bali

Shanny Poijes · Developer in Indonesia (director, PT Core Group Indonesia) · Background in project management and advisory
Last verified 15 August 2026 · checked for changes 21 November 2026

Zoning in Bali is a stack of plans. The province and each regency have a spatial plan, called the RTRW. A district can also have a detailed plan, called the RDTR.

The RDTR gives every block a zone code. The code sets which activities are allowed on the land. It also sets how much of the plot you may cover and how high you may build.

Overlays sit on top of the zone. Coastal, cliff, temple and farmland lines apply whatever the zone says. A tourism zone does not defeat them.

The national framework changed on 28 July 2026. PP 34/2026 on spatial planning took effect that day and revoked PP 21/2021. Rules made under the old regulation stay in force where they do not conflict. This page does not yet reflect the rest of the new text.

What the law says

Perda Bali 2/2023, Article 144

Perda Bali 2/2023 is the provincial spatial plan for 2023 to 2043. Article 144 revokes the older plans, Perda Bali 16/2009 and Perda Bali 3/2020.

Perda Bali 2/2023, Article 100(2)

Arahan ketinggian bangunan secara umum di Wilayah Provinsi dibatasi maksimum 15 m (lima belas meter) diatas permukaan tanah tempat bangunan didirikan.

Building height across the province is limited to 15 m above the ground where the building stands. Article 100(4) allows a closed list of ten exceptions.

Perda Bali 2/2023, Article 95

In a tourism area the plan permits accommodation and tourism facilities. Housing is allowed only with conditions. Coverage is capped at 50% and height at 15 m. Parking must be at least 20% of floor area.

Perda Badung 4/2025, Article 96

In Badung's tourism area, limited-intensity housing is conditional and intensive housing is not allowed. The plan does not define either term. Article 96(e) leaves the line to the detailed plan and the spatial planning forum.

Perbup Badung 34/2022, Article 42(6)

This is the detailed plan for Mengwi district. It cuts sub-zone R-4, low-density housing, to 9 m. The cut covers housing, trade and services, tourist accommodation, industry and private offices. Its Annex VII keeps 15 m for zones W, R-2 and R-3.

Perpres 51/2016, Article 1(2)

Sempadan pantai adalah daratan sepanjang tepian pantai, yang lebarnya proporsional dengan bentuk dan kondisi fisik pantai, minimal 100 (seratus) meter dari titik pasang tertinggi ke arah darat.

The coastal setback is defined as at least 100 m from the highest tide line. It is one of the overlays that sit on top of the zone.

Permen ATR/BPN 13/2021, Article 2

Every use of space needs a KKPR (the spatial conformity approval) first. The KKPR tests the planned activity against the spatial plan for that location.

PP 34/2026, Articles 289 to 291

PP 34/2026 on the implementation of spatial planning has been in force since 28 July 2026. Article 290 revokes PP 21/2021. Article 289 keeps the implementing regulations of PP 21/2021 in force where they do not conflict.

What it means

The zone settles use. It does not settle how much you can build. Draw the coastal, cliff and temple lines on the title survey before you value land.

Each RDTR carries an activity table. An activity is marked I for allowed, T for limited, B for conditional or X for not allowed. Read the row for your exact activity, not the zone name.

The Badung tables show how much the code matters. A villa, meaning tourist accommodation, is marked X in residential zones R-2 to R-4. A house is allowed there. In Mengwi and Kuta Selatan, a villa is allowed in zones W, K-1, K-2 and C-2.

Zone numbering can mislead. In the Mengwi plan, R-2 is high-density housing and R-4 is low-density housing. R-4 is also the sub-zone capped at 9 m, below the provincial 15 m.

Plans are replaced over time. Badung adopted a regency RTRW for 2025 to 2045, Perda Badung 4/2025. An approval assessed under an older plan can give a different result when tested again.

Coverage differs by regency. Provincial data from February 2026 showed Badung fully covered by RDTR and Tabanan at 21.43%. Where no integrated RDTR exists, the approval runs on a slower manual track.

A setback line drawn in a seller's documents can differ from the statutory line. When the two disagree, recompute the line from the regulation.

What to check

  • Identify which RDTR covers the plot and the year it was issued.
  • Read the zone code and the activity table row for your exact use.
  • Ask for the coverage ratio, floor area ratio, green area share and height limit for the zone.
  • Overlay the coastal, cliff, temple and farmland lines on the title survey.
  • Check whether any approval in the seller's file was assessed under a plan that has been replaced.
  • Recompute any setback or area figure shown in seller documents.
  • Check how PP 34/2026 and its implementing rules apply on the date you file.
Questions

What is the difference between RTRW and RDTR?

The RTRW is the general spatial plan of the province or regency. The RDTR is the detailed plan for a district. The RDTR carries the zone codes, building ratios and activity table.

Does a tourism zone mean I can build anywhere on the plot?

No. Coastal, cliff, temple and height rules apply on top of the tourism zone. They can remove most of the buildable area.

Is Perda Bali 16/2009 still the Bali spatial plan?

No. Perda Bali 2/2023 revoked it, together with Perda Bali 3/2020. Many property guides still cite the old regulation.

Sources
  • Perda Provinsi Bali 2/2023, provincial spatial plan (RTRW) 2023 to 2043
  • Perda Kabupaten Badung 4/2025, regency spatial plan (RTRW) 2025 to 2045
  • Perbup Badung 34/2022, detailed spatial plan (RDTR) for Mengwi district
  • Perpres 51/2016 on coastal setback boundaries
  • Permen ATR/BPN 13/2021 on KKPR
  • PP 34/2026 on the implementation of spatial planning (State Gazette 2026 No. 93), which revoked PP 21/2021
  • Badung regency public zoning service (DPUPR Kabupaten Badung)

General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.

Read nextThe library

How to check the zoning of a plot in Badung, Bali

Badung regency runs a public zoning service. For a parcel it returns the zone, farmland overlay, building ratios, setbacks, height and permitted uses.

Building height, coastal setback, cliffs and temples in Bali

Bali caps buildings at 15 m with ten closed exceptions. The coastal setback is at least 100 m from the highest tide line. Cliffs and temples add more.

KKPR: the spatial approval that comes before a build in Indonesia

KKPR confirms that a planned activity fits the spatial plan at that location. It comes before the building approval, and it gates an HGB grant.

Rice fields and protected farmland in Bali: LSD, LP2B and release letters

A rice field in Bali can carry three separate locks: the LSD map, LP2B status and the zone. A ministry release letter touches only the first.