Environmental approval and groundwater permits for a build in Bali

Shanny Poijes · Developer in Indonesia (director, PT Core Group Indonesia) · Background in project management and advisory
Last verified 21 November 2026

Every planned business or activity that affects the environment must hold one of three environmental documents. The AMDAL is a full impact assessment. The UKL-UPL is a standard management and monitoring form, and the SPPL is a statement of commitment.

Which one applies depends on impact, scale and location. A plan with significant impact, or one inside or directly bordering a protected area, needs an AMDAL. Smaller plans fall to the UKL-UPL or the SPPL.

Groundwater has its own rule. Using groundwater for a business needs a groundwater business licence first. Non-business use needs an approval, with an exemption for small household use.

This page covers the national rules only. I have not read the ministerial list that sorts project types into the three documents, or any regency rule.

What the law says

PP 22/2021, Article 3(1) and (3)

Government Regulation 22 of 2021 on environmental protection and management requires an environmental approval for every business or activity with significant or non-significant impact. The approval is a precondition for the business licence.

PP 22/2021, Article 4

Every planned business or activity that affects the environment must have an AMDAL, a UKL-UPL or an SPPL.

PP 22/2021, Article 5(1) and (2)

An AMDAL is required for plans with significant impact. That covers types that qualify by size or scale, and plans located inside or directly bordering a protected area.

PP 22/2021, Article 6

A UKL-UPL is required for plans without significant impact that sit outside, and do not directly border, a protected area.

PP 22/2021, Article 7

An SPPL is required for plans without significant impact that are not UKL-UPL types. This includes micro and small businesses without significant impact.

PP 22/2021, Article 10(1)(a)

The AMDAL duty is lifted where the regency has a detailed spatial plan that is completed with a comprehensive strategic environmental study.

Permen ESDM 4/2026, Article 2(2) and (3)

Penggunaan Sumber Daya Air pada Air Tanah untuk kegiatan usaha sebagaimana dimaksud pada ayat (1) huruf a dilakukan setelah memiliki Izin Pengusahaan Air Tanah.

Minister of Energy and Mineral Resources Regulation 4 of 2026 has been in force since 22 January 2026. Business use of groundwater is allowed only after a groundwater business licence is held. Non-business use needs a groundwater use approval.

Permen ESDM 4/2026, Article 6(1) and (2)

An approval is needed for daily household needs of 100 m3 per month or more per head of family, and for dewatering. No approval is needed for daily household needs below 100 m3 per month.

What it means

Settle the environmental document early. It is a precondition for the business licence, so a late start holds up everything behind it.

Location can change the answer. A site inside or directly bordering a protected area moves a plan toward an AMDAL. Article 10 lists exemptions.

The minister reviews the lists of project types at least every 5 years, under Article 9. Ask an environmental consultant which list is current. How the approval is ordered against the PBG (the building approval) is not settled in the texts I read.

The regulation lists tourism and housing among the fields of business use. A borewell for a hotel, a rental villa or a housing project likely falls there. The licence application runs through the OSS licensing system.

A private home using less than 100 m3 a month for daily needs is exempt from the national approval. I have not checked Bali provincial or regency groundwater rules, which may add to this.

Dewatering needs an approval. Check this before any basement or deep excavation below the water table.

Article 46 of the 2026 regulation revoked the approval, supervision and sanction rules of Permen ESDM 14/2024. The official regulation database lists the 2024 regulation as revoked. Advice written before 22 January 2026 may quote the old text.

For electricity and piped water connections I have read no legal text. Ask the electricity company and the local water utility for a written quote and lead time before you fix the programme.

For electricity, an official table of residential power upgrade charges dates from August 2026. Kompas reported it on 14 August 2026.

An upgrade from 1,300 VA to 7,700 VA was Rp 6,201,600. From 3,500 VA it was Rp 4,069,800, and from 5,500 VA it was Rp 2,131,800.

For a connection above 7,700 VA, ask PLN (the state electricity company) for a written quote.

What to check

  • Ask an environmental consultant in writing which document your project needs and why.
  • Check whether the site is inside or directly borders a protected area.
  • Ask the regency whether its detailed spatial plan changes the AMDAL duty for your zone.
  • Confirm in writing when the regency wants the environmental document relative to the PBG.
  • Decide early whether the water source is a borewell or a utility connection.
  • Apply for the groundwater licence or approval before drilling.
  • Ask the regency and province about local groundwater rules and charges.
  • Request written connection quotes from the electricity and water utilities.
Questions

Does a villa in Bali need an AMDAL?

It depends on impact, scale and location. PP 22/2021 requires an AMDAL for significant impact or a site inside or bordering a protected area. Other plans need a UKL-UPL or an SPPL, and a consultant should confirm the class.

What is an SPPL?

It is a statement of commitment to manage and monitor the environment. PP 22/2021 Article 7 applies it to plans without significant impact that do not need a UKL-UPL.

Do I need a permit for a borewell in Indonesia?

For business use, yes. A groundwater business licence must be held first. For a household using less than 100 m3 a month for daily needs, the national regulation requires no approval.

Is the environmental approval needed before the business licence?

Yes. PP 22/2021 Article 3(3) makes it a precondition for issuing the business licence.

What does a PLN power upgrade to 7,700 VA cost?

The August 2026 residential table gave Rp 6,201,600 from 1,300 VA and Rp 4,069,800 from 3,500 VA. From 5,500 VA it gave Rp 2,131,800. Ask PLN for a written quote, because charges change.

General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.

Read nextThe library

PBG: the building approval in Bali and whose name it is in

A PBG is issued to the building owner before construction. It cannot be moved to another name. Anyone can request a copy from the regency.

KKPR: the spatial approval that comes before a build in Indonesia

KKPR confirms that a planned activity fits the spatial plan at that location. It comes before the building approval, and it gates an HGB grant.

How zoning works in Bali

Bali zoning is a stack of plans. The zone code sets the permitted use. Coastal, cliff, temple and farmland overlays decide what you can build.

Taxes and statutory charges on building a villa in Bali

A VAT-registered contractor charges 11% PPN. A self-build of 200 m2 or more pays 2.2% on build costs. PPh final, BPJS and the PBG fee also apply.