SLF: the certificate of fitness for a building in Bali
SLF (Sertifikat Laik Fungsi, the certificate of fitness for use) certifies that a finished building is fit to be used. A business must hold it before it uses the building.
The textbook order is spatial approval, then PBG (the building approval), then construction, then SLF. The regency issues the SLF on a fitness statement from the supervising consultant, uploaded with as-built drawings.
A building that already stands without a PBG has its own route. A certified technical assessor checks it, and the PBG for the existing building is issued together with the SLF.
What the law says
PP 16/2021, Articles 60(6) and 272(4), (6)
Government Regulation 16 of 2021 implements the Building Law. The supervision or construction management consultant issues the statement of fitness for use from its checklist, before final handover.
PP 16/2021, Article 272(11)
The fitness statement is uploaded together with as-built drawings.
PP 16/2021, Articles 274 and 276
The regency office issues the SLF and the SBKBG, a building ownership document, within 3 working days. Issue is free of charge.
PP 16/2021, Article 273
A cluster of buildings with the same design needs one fitness statement for each building.
PP 16/2021, Articles 210(b) and 212
An existing building without a PBG gets its first SLF after a check by a certified technical assessor (Pengkaji Teknis). The check covers documents, the building's condition against the technical standards, analysis and a report.
PP 16/2021, Article 262(1) and (4)
A PBG for an existing building is issued together with the SLF.
PP 28/2025, Article 122(1)
Under the business licensing regulation, the business must obtain the SLF before the building is used.
SNI 03-1735-2000, clauses 4.2.1 to 4.2.3, with PP 16/2021, Article 30(1)
PP 16/2021 makes fire protection of the building and the site mandatory, and the national fire access standard sets the widths. Where the highest occupied floor is at most 10 m above ground, no hardstanding is required. A 4 m operational strip, reachable within 45 m of the fire-truck route, is enough.
PP 16/2021, Article 297(1) and (2)
20 (dua puluh) tahun untuk rumah tinggal tunggal dan deretAn SLF must be extended at a set interval. The interval is 20 years for a single house and a row house. It is 5 years for every other building.
PP 16/2021, Article 297(3) to (7)
Perpanjangan SLF sebagaimana dimaksud pada ayat (1) didahului dengan pemeriksaan kelaikan fungsi.A fitness inspection comes before the extension. It compares the site and the as-built drawings with the last SLF and the technical standards. The owner or user pays for the inspection.
PP 16/2021, Article 298(1), (2) and (8)
A technical assessment service provider carries out the inspection. For a single house or row house the regency technical office may do it, for a levy.
PP 16/2021, Articles 299 and 301
A building found not yet fit receives a recommendation for repair, for a PBG update, or for both. Where a PBG update with repair is needed, the owner may apply for a temporary use letter. That letter cannot be extended.
SLF dan surat keterangan pemanfaatan sementara sebagaimana dimaksud pada ayat (2) diterbitkan tanpa dipungut biaya.Article 302 sets the consequence when the SLF and any temporary use letter are no longer valid. The building ownership document lapses and regency utility services are withdrawn until an SLF is obtained again. The extended SLF is issued free of charge through the SIMBG system.
UU 28/2002, Article 37(5), as amended by UU 6/2023
Pemeliharaan, Perawatan, dan Pemeriksaan Berkala pada Bangunan Gedung harus dilakukan untuk memastikan Bangunan Gedung tetap memenuhi persyaratan laik fungsi.The Building Law requires maintenance, upkeep and periodic inspection so the building stays fit for use. The law itself sets no validity period.
What it means
The SLF is the document that makes a building lawfully usable. Ask for it, and do not treat a PBG alone as the end of the permit trail.
Fire access is checked at PBG and SLF. A common claim is that Indonesian standards require 6 m of clear fire-truck access on every internal road. The standard does not say that for low-rise housing.
In SNI 03-1735-2000 the 6 m figure is a hardstanding pad, 6 m wide and 15 m long, at the fire-access opening. Other parts of the fire-truck route must not be less than 4 m. That clause excludes dwellings.
Access lanes of 6 m are required for non-residential buildings such as factories and warehouses, and for residential buildings above 10 m. Where a pad or lane is required it must be kept free of obstruction and marked.
The same standard limits a dead end to 46 m before a turning facility. It sets an outer turning radius of at least 10.5 m. A regency may apply a stricter local rule, so get the desk's position in writing.
Whether the SLF strictly requires the finished building to match the approved PBG drawings is an open question. Have the permit consultant answer it in writing for your regency.
For a cluster of identical units, expect one fitness statement for each building.
Parking is checked on the way to the SLF. Perda Bali 2/2023 Article 95 sets tourism-area parking at a minimum of 20% of floor area.
An SLF does not last for the life of the building. A single house or row house needs an extension every 20 years. Every other building needs one every 5 years.
The regulation does not name villas. Single houses and row houses are residential types, and hotel-type buildings are business buildings. Ask the regency desk in writing which interval applies to the building as it is classified.
The text read for this page does not say from which date the interval counts. Ask the desk to state the extension date in writing.
At extension the building is tested against its last SLF. Changes made since then can lead to a PBG update before the extension is granted.
A buyer of an older building should read the date on the SLF. A certificate past its interval needs an inspection and an extension application.
In practice
Practitioners report that in Bali the PBG is not treated as a hard precondition for an SLF application. Commonly used routes secure the SLF with the PBG regularised alongside or afterwards.
Practitioners report that this route is narrowing. It becomes harder and more expensive each year. Anyone holding a building without a PBG should treat the shrinking window as a risk a buyer will see.
For a building that already stands, practitioners report that the application goes in on new as-built drawings showing the building as it is. Desks are currently strict on parking.
Practitioners report that an SLF often comes through even where the building falls short on site coverage, parking or setbacks. Meeting the limits makes it easier. Falling short does not automatically block it.
Practitioners report that the usual desk requirement for parking is 20% of floor area.
What to check
- Ask the seller for the SLF, and not only the PBG.
- Check that the SLF and the PBG state the same function as the use you intend.
- Ask who issued the fitness statement and request a copy with the as-built drawings.
- Ask any consultant who demands 6 m clear internal roads to cite the clause.
- Get the regency desk's fire-access and parking position in writing.
- Ask the permit consultant in writing whether as-built deviations from the PBG block the SLF in that regency.
- Treat a building with no PBG and no SLF as a permit risk and price the time to regularise it.
What does an SLF certify?
It certifies that the finished building is fit for use. It rests on the supervising consultant's fitness statement and the as-built drawings.
How much does an SLF cost?
PP 16/2021 Articles 274 and 276 make the issue of the SLF free and set 3 working days for it. Consultant work to prepare the file is a separate cost.
Can an existing building without a PBG get an SLF?
Yes. PP 16/2021 Articles 210(b) and 212 provide a check by a certified technical assessor. Under Article 262 the PBG for the existing building is issued with the SLF.
Does a villa compound need 6 m fire roads?
The national standard does not require that for low-rise housing. Its figure for the route is 4 m, with carve-outs where the highest occupied floor is at most 10 m. A regency may be stricter.
Does an SLF expire and need renewing in Indonesia?
PP 16/2021 Article 297 requires an SLF to be extended at a set interval. That interval is 20 years for a single house or row house. It is 5 years for other buildings.
How is an SLF extended in Bali?
A technical assessor inspects the building against the last SLF and the technical standards. With a fitness statement, the owner or user applies to the regency through SIMBG.
What does an SLF extension cost?
The extended SLF is issued free of charge under Article 302(3). The owner or user pays for the fitness inspection under Article 297(7).
What happens if the SLF is not extended?
Under Article 302(1) the building ownership document lapses and regency utility services are withdrawn. That applies until the owner or user obtains an SLF again.
- Government Regulation (PP) 16 of 2021, implementing the Building Law (UU 28/2002)
- Government Regulation (PP) 28 of 2025 on risk-based business licensing
- SNI 03-1735-2000, the national standard on fire access planning for buildings
- Minister of Public Works Regulation 26/PRT/M/2008, which applies the standard
- Perda Provinsi Bali 2/2023, provincial spatial plan (RTRW) 2023 to 2043, Article 95
- PP 16/2021, Articles 297 to 302 on extending the SLF, JDIH BPK record page
- UU 6/2023, which replaced Article 37 of the Building Law (UU 28/2002), JDIH BPK record page
General information, not legal, tax or investment advice. Your position depends on your circumstances, so take your own case to a property lawyer before you sign or pay.