The obligation to build: idle land rules in Indonesia
An HGB (right to build) or Hak Pakai (right to use) title carries a build deadline. The holder must build or work the land within two years of the grant. This duty is separate from the building approval.
From two years after issue, idle land can be listed as indicated abandoned. After an evaluation and three warnings, the Minister can declare it abandoned. The title is then extinguished and the land returns to the state.
PP 48/2025 has governed this since 6 November 2025. It cut the maximum process from more than 500 days to about 90. A sale of the land does not restart the two-year clock.
The rule is national. It applies the same way in Bali, Lombok and everywhere else. Hak Milik (freehold held by Indonesian citizens) is largely outside it.
A lessee under a lease (hak sewa) is not an object of this regime. The duty sits on the title holder, so a lessee should check how the lessor's own title stands.
What the law says
melaksanakan pembangunan dan/atau mengusahakan tanahnya sesuai dengan tujuan peruntukan dan persyaratan sebagaimana ditetapkan dalam keputusan pemberian haknya paling lama 2 (dua) tahun sejak hak diberikanThe HGB holder must build or work the land within two years of the grant. Article 57(a) uses identical wording for Hak Pakai.
PP 18/2021, Article 46(b) and (g)
An HGB ends if the Minister cancels it for breach of the holder's duties. It also ends for breach of a land-use agreement with the underlying right holder. Designation as abandoned land ends it too.
This covers HGB over HPL (a state management right). Extension or renewal is possible only if the land has been used for its purpose. An unbuilt plot has no extension.
PP 48/2025, Article 6(3) to (5)
jika dengan sengaja tidak diusahakan, tidak dipergunakan, tidak dimanfaatkan, dan/atau tidak dipelihara terhitung paling cepat 2 (dua) tahun sejak diterbitkannya hakHGB, Hak Pakai and HPL land becomes an object if deliberately left unworked, unused or unmaintained. The earliest point is two years from issue of the right.
PP 48/2025, Elucidation of Article 6(3)
tetap berlaku walaupun terjadi perbuatan hukum dan/atau peristiwa hukumThe two years keep running through any legal act or legal event. A buyer inherits the seller's elapsed time.
Hak Milik is not an object unless it is deliberately unused and one more condition is met. The conditions are settlement by the community, 20 years of holding by others, or an unmet social function.
PP 48/2025, Articles 23, 25 and 27
Evaluation takes 12 days and the cure window 30 days. Three warnings of 14 days each follow. The regional office then has 6 days to propose designation to the Minister.
Designation extinguishes the right and the land becomes state land. The holder must vacate within 30 days. An objection goes through the administrative court.
What it means
The elucidation of Article 6(2) lists four excuses. They are a court case over the land and a spatial-plan change that makes use impossible. The other two are a conservation designation and declared force majeure.
A slow building approval is not on that list. Nor is a refused spatial approval, a financing delay or a licensing block.
Article 6 also covers land held on a possession basis, such as an unregistered sale deed. Ministry officials said in July 2025 that the priority is HGU and HGB held by legal entities.
On a partial finding, the abandoned part is cut out and a boundary revision ordered. If the holder does not complete it within 180 days, the whole parcel becomes abandoned land.
A lessee under Hak Sewa (a lease) is not an object of the regime. The lessor's title is. A lessor's idle HGB or Hak Pakai can be extinguished under the tenant. A lease over Hak Milik land is largely outside that exposure.
Land over HPL carries a second, contractual deadline in the land-use agreement. On Gili Trawangan, the West Nusa Tenggara government ended a 1995 contract over 65 ha. It did so on 22 February 2021, after the promised buildings were never built.
Officials said in July 2025 that fencing, planting and clearing count as use. The elucidation says land that is only maintained can still be an object. The position is unsettled, so do not rely on a fence alone.
In practice
Practitioners report that a first HGB or Hak Pakai application requires a signed two-year build undertaking. They also report a clearance that the plot is not in the indicated-abandoned database.
What to check
- Read the issue date on the certificate of any unbuilt HGB or Hak Pakai plot.
- Ask the land office whether the plot is in the indicated-abandoned database.
- Read the build condition printed in the grant decision and on the certificate.
- Start visible works within 24 months of the grant and keep dated evidence.
- Read the land-use agreement for its own build milestones where the title sits over HPL.
- Check the landlord's title type and build status before you lease land held under HGB or Hak Pakai.
How long do I have to build on HGB land in Indonesia?
Two years from the grant, under PP 18/2021. The condition is written into the grant decision and onto the certificate.
Does buying the land restart the two-year clock?
No. The elucidation of PP 48/2025 says the period keeps running through any legal act. The buyer takes over the seller's elapsed time.
Is there a special rule for Lombok?
No regional title rule was found for Lombok or its province. The national regulations apply, plus any contract deadline on land over HPL.
- PP 18/2021 on management rights, land rights, strata units and land registration
- PP 48/2025 on control of abandoned areas and abandoned land (replaces PP 20/2021)
- Permen ATR/BPN 18/2021 (Article 39, build duty of the HPL holder)
- BPK regional office for West Nusa Tenggara, news note of February 2021 on the Gili Trawangan contract
- Ministry of Agrarian Affairs statements, 16 to 22 July 2025